Case Study: Casanet Warehouse — WMS Adoption 88% + Efficiency +40%

Client Profile

Secteur: Distribution (Maroc Telecom subsidiary) Taille: 25 warehouse staff, 2000 m² facility Localisation: Casablanca Problem: WMS implemented but underutilized (42% adoption)


Baseline Problem

Situation

  • WMS in place but users prefer Excel
  • Adoption only 42% (vs 80%+ expected)
  • Stock accuracy: 78% (vs 94%+ target)
  • Picking errors: 3.2% (vs <1% target)
  • Cycle time: 2.8 days

Root Cause Analysis

  • Training was 2 days only (insufficient)
  • No on-job coaching
  • Process design misaligned with WMS logic
  • Users didn't understand "why" WMS

Intervention: Consulting + Training (6 mois)

Phase 1: Process Audit (2 sem)

  • Understand current manual process
  • Identify WMS misalignment
  • Design optimized process

Phase 2: Training Bootcamp (1 week)

  • Intensive 3-day training (vs prior 2 days)
  • Hands-on: Real warehouse scenarios
  • Deep-dive: Reports, workflows, advanced features
  • Job aids: Quick reference guides

Phase 3: On-Job Coaching (8 weeks)

  • 1 day/week on-site coaching
  • Real problem solving
  • Process refinement
  • Change management support

Phase 4: Stabilisation (2 weeks)

  • KPI monitoring
  • User feedback incorporation
  • Final optimization

Results (3 mois post go-live)

Adoption & Engagement

WMS Adoption: 42% → 88%
User Satisfaction: 65% → 92%
Feature utilization: 30% → 85%
Training completion: 50% → 100%

Operational Metrics

MetricBaselinePostGain
Stock accuracy78%94%+16pts
Picking error rate3.2%0.8%-75%
Cycle time2.8 days1.4 days-50%
Picking speed1h/100 items25min/100 items-58%
Downtime incidents2x/week0.2x/week-90%

Financial Impact

Consulting + Training cost: 320K MAD
Benefits Year 1:
- Labor efficiency: 600K
- Error reduction: 400K
- Inventory optimization: 200K
- Total: 1.2 MMAD
ROI: 3.75x | Payback: 3 months

Key Success Factors

  1. Process-First Approach: Design process THEN implement WMS (not reverse)
  2. Intensive Training: 3 days + 8 weeks coaching >> 2 days alone
  3. Management Sponsor: Weekly check-ins → User compliance
  4. Quick Wins: Week 1 → 15% time reduction visible → Motivation

Timeline & Cost

PhaseDurationCost
Audit2 weeks20K
Training1 week30K
Coaching8 weeks200K
Support2 weeks30K
Technology-40K
Total6 months320K MAD

Client Quote

"WMS was dead in water before Nextinotech. One week of intense training + 8 weeks coaching = completely different adoption story. 88% vs 42% adoption, users now love the system. ROI fantastic, best investment we made in operations."

>

— Warehouse Manager, Casanet

Lesson: Change Management is 70% of Success

  • Technology alone: 40% adoption
  • Technology + light training: 50% adoption
  • Technology + intensive training + coaching: 85%+ adoption

Adoption multiplies ROI exponentially.


Nextinotech — WMS Implementation Expertise + Change Management